The Head of “Rosseti” has checked readiness of central regions of the country for the winter

The Head of “Rosseti” has checked readiness of central regions of the country for the winter

5 October 2015, 04:57
Tags: Rosseti

1617 views

General director of PJSC “Rosseti” Oleg Budargin has held a meeting on the course of preparations of objects of the electric grid complex of subsidiary PJSC “MRSK Tsentra” for the forthcoming autumn and winter period 2015-2016.

There are 11 subjects of the RF of a total number of more than 13 million people in a zone of servicing of PJSC “MRSK Tsentra”.
During the event the leadership of MRSK Tsentra reported that preparations for passing autumn and winter maximum of loads in PJSC “MRSK Tsentra” entered the final phase. The company has been finishing realization of the main events of a repair program and in its offices the second stage of the check, preceding getting of the Passport of readiness for work in the autumn and winter period 2015-2016, started.

The main volume of works of MRSK Tsentra have been finished. Specialists of the company have done complex repair of 139 35-110 kV substations, have repaired 3839 transformater 0,4-110 kV substations and about 14,1 thousand km of air and cable 0,4-110 kV power lines.

Between September 21st and October 2nd all the offices of PJSC “MRSK Tsentra” will be checked by joint committees. Representatives of territory administrations of Rostehnadzor and regional administrations of the Ministry of Emergency Situations (Russia), MRSK Tsentra will comprise this committees. In the case of absence of reproofs and defects the offices will be given the Passports of readiness for work in the autumn and winter period 2015-2016.

In its turn the commission of the Ministry of power engineering of the Russian Federation will be checking readiness of PJSC “MRSK Tsentra” for the autumn and winter period 2015-2016. According to the schedule chart this work must be finished till October 9th. In this time, as it is expected, the company will be given the Passport of readiness.

Concluding the results of the meeting, Oleg Budargin said that the main task of power engineers was reliability of electric supply of customers despite the macroeconomic situation and tariff decisions. “Reliability is first of all a reliable staff. I want to thank the leadership of MRSK Tsentra and the offices for remaining professionals in the staff of the company. Due to their everyday labour good indices in the first half year were reached and there is confidence in stable passing of the forthcoming autumn and winter period”, the Head of “Rosseti” added.